Dispatch Instructions

Transmission Network Operating Limits
Information about Transmission Network operating limits for the period from October 1, 2024 to May 1, 2025

The transmission network operating limits for the period from October 1, 2024 to May 1, 2025 were approved under Order No 82 of September 27, 2024 of JSC Georgian State Electrosystem. The basis for the abovementioned order is Article 47 (3) (e) of the “Network Code” approved by Decree No.10 of April 17, 2014 of the Georgian National Energy and Water Supply Regulatory Commission and the Instructions for setting network operating limits approved by Order # 408 of July 21, 2016. "The primary source of establishing the transmission network operating limits is information received from JSC United Energy System Sakrusenergo, regional networks of JSC Georgian State Electrosystem, JSC Telasi and JSC Energo-Pro Georgia.

Transmission Network Operating Limits
Information about Transmission Network operating limits for the period from May 1, 2024 to October 1, 2024

The transmission network operating limits for the period from May 1, 2024 to October 1, 2024 were approved under Order No 26 of April 30, 2024 of JSC Georgian State Electrosystem. The basis for the abovementioned order is Article 47 (3) (e) of the “Network Code” approved by Decree No.10 of April 17, 2014 of the Georgian National Energy and Water Supply Regulatory Commission and the Instructions for setting network operating limits approved by Order # 408 of July 21, 2016. "The primary source of establishing the transmission network operating limits is information received from JSC United Energy System Sakrusenergo, regional networks of JSC Georgian State Electrosystem, JSC Telasi and JSC Energo-Pro Georgia.

Transmission Network Operating Limits
Information about Transmission Network operating limits for the period from from October 1, 2023 to May 1, 2024

The transmission network operating limits for the period from October 1, 2023 to May 1, 2024 were approved under Order No 96 of September 27, 2023 of JSC Georgian State Electrosystem. The basis for the abovementioned order is Article 47 (3) (e) of the “Network Code” approved by Decree No.10 of April 17, 2014 of the Georgian National Energy and Water Supply Regulatory Commission and the Instructions for setting network operating limits approved by Order # 408 of July 21, 2016. "The primary source of establishing the transmission network operating limits is information received from JSC United Energy System Sakrusenergo, regional networks of JSC Georgian State Electrosystem, JSC Telasi and JSC Energo-Pro Georgia.

Transmission Network Operating Limits
Information about Transmission Network operating limits for the period from May 1, 2023 to October 1, 2023

The transmission network operating limits for the period from May 1, 2023 to October 1, 2023 were approved under Order No 41 of April 26, 2023 of JSC Georgian State Electrosystem. The basis for the abovementioned order is Article 47 (3) (e) of the “Network Code” approved by Decree No.10 of April 17, 2014 of the Georgian National Energy and Water Supply Regulatory Commission and the Instructions for setting network operating limits approved by Order # 408 of July 21, 2016. "The primary source of establishing the transmission network operating limits is information received from JSC United Energy System Sakrusenergo, regional networks of JSC Georgian State Electrosystem, JSC Telasi and JSC Energo-Pro Georgia.

Transmission Network Operating Limits
Information about Transmission Network operating limits for the period from October 1, 2022 to May 1, 2023

The transmission network operating limits for the period from October 1, 2022 to May 1, 2023 were approved under Order No 94 of September 29, 2022 of JSC Georgian State Electrosystem. The basis for the abovementioned order is Article 47 (3) (e) of the “Network Code” approved by Decree No.10 of April 17, 2014 of the Georgian National Energy and Water Supply Regulatory Commission and the Instructions for setting network operating limits approved by Order # 408 of July 21, 2016. "The primary source of establishing the transmission network operating limits is information received from JSC United Energy System Sakrusenergo, regional networks of JSC Georgian State Electrosystem, JSC Telasi and JSC Energo-Pro Georgia.

Transmission Network Operating Limits
Information about Transmission Network operating limits for the period from May 1, 2022 to October 1, 2022

The transmission network operating limits for the period from May 1, 2022 to October 1, 2022 were approved under Order No 24 of April 27, 2022 of JSC Georgian State Electrosystem. The basis for the abovementioned order is Article 47 (3) (e) of the “Network Code” approved by Decree No.10 of April 17, 2014 of the Georgian National Energy and Water Supply Regulatory Commission and the Instructions for setting network operating limits approved by Order # 408 of July 21, 2016. "The primary source of establishing the transmission network operating limits is information received from JSC United Energy System Sakrusenergo, regional networks of JSC Georgian State Electrosystem, JSC Telasi and JSC Energo-Pro Georgia.

Transmission Network Operating Limits
Information about Transmission Network operating limits for the period from October 1, 2021 to May 1, 2022

The transmission network operating limits for the period from October 1, 2021 to May 1, 2022 were approved under Order No 81 of September 28, 2021 of JSC Georgian State Electrosystem. The basis for the abovementioned order is Article 47 (3) (e) of the “Network Code” approved by Decree No.10 of April 17, 2014 of the Georgian National Energy and Water Supply Regulatory Commission and the Instructions for setting network operating limits approved by Order # 408 of July 21, 2016. "The primary source of establishing the transmission network operating limits is information received from JSC United Energy System Sakrusenergo, regional networks of JSC Georgian State Electrosystem, JSC Telasi and JSC Energo-Pro Georgia.

Transmission Network Operating Limits
Information about Transmission Network operating limits for the period from May 1, 2021 to October 1, 2021

The transmission network operating limits for the period from May 1, 2021 to October 1, 2021 were approved under Order No 39 of April 26, 2021 of JSC Georgian State Electrosystem. The basis for the abovementioned order is Article 47 (3) (e) of the “Network Code” approved by Decree No.10 of April 17, 2014 of the Georgian National Energy and Water Supply Regulatory Commission and the Instructions for setting network operating limits approved by Order # 408 of July 21, 2016. "The primary source of establishing the transmission network operating limits is information received from JSC United Energy System Sakrusenergo, regional networks of JSC Georgian State Electrosystem, JSC Telasi and JSC Energo-Pro Georgia.

Transmission Network Operating Limits
Information about Transmission Network operating limits for the period from October 1, 2020 to May 1, 2021

The transmission network operating limits for the period from October 1, 2020 to May 1, 2021 were approved under Order No 116 of September 25, 2020 of JSC Georgian State Electrosystem. The basis for the abovementioned order is Article 47 (3) (e) of the “Network Code” approved by Decree No.10 of April 17, 2014 of the Georgian National Energy and Water Supply Regulatory Commission and the Instructions for setting network operating limits approved by Order # 408 of July 21, 2016. "The primary source of establishing the transmission network operating limits is information received from JSC United Energy System Sakrusenergo, Energotrans Ltd, regional networks of JSC Georgian State Electrosystem, JSC Telasi and JSC Energo-Pro Georgia.

Transmission Network Operating Limits
Information about Transmission Network operating limits for the period from May 1, 2020 to October 1, 2020

The transmission network operating limits for the period from May 1, 2020 to October 1, 2020 were approved under Order No 4518 of April 23, 2020 of JSC Georgian State Electrosystem. The basis for the abovementioned order is Article 47 (3) (e) of the “Network Code” approved by Decree No.10 of April 17, 2014 of the Georgian National Energy and Water Supply Regulatory Commission and the Instructions for setting network operating limits approved by Order # 408 of July 21, 2016. "The primary source of establishing the transmission network operating limits is information received from JSC United Energy System Sakrusenergo, Energotrans Ltd, regional networks of JSC Georgian State Electrosystem, JSC Telasi and JSC Energo-Pro Georgia.

Transmission Network Operating Limits
Information about Transmission Network operating limits for the period from October 1, 2019 to May 1, 2020

The transmission network operating limits for the period from October 1, 2019 to May 1, 2020 were approved under Order No 166 of October 1, 2019 of JSC Georgian State Electrosystem. The basis for the abovementioned order is Article 47 (3) (e) of the “Network Code” approved by Decree No.10 of April 17, 2014 of the Georgian National Energy and Water Supply Regulatory Commission and the Instructions for setting network operating limits approved by Order # 408 of July 21, 2016. "The primary source of establishing the transmission network operating limits is information received from JSC United Energy System Sakrusenergo, Energotrans Ltd, regional networks of JSC Georgian State Electrosystem, JSC Telasi and JSC Energo-Pro Georgia.

Transmission Network Operating Limits
Information about Transmission Network Operating Limits for the period of May 1, 2019 to October 1, 2019

The transmission network operating limits for the period from May 1, 2019 to October 1, 2019 were approved under Order No 86 of May 15, 2019 of JSC Georgian State Electrosystem. The basis for the Order is Article 47(3)(e) of the Network Code approved by Decree No 10 of April 17, 2014 of the Georgian National Energy and Water Supply Regulatory Commission and the Instructions for Establishing the Transmission Network Operating Limits approved by Order No 408 of July 21, 2016. The primary source of establishing the transmission network operating limits is information received from JSC United Energy System Sakrusenergo, Energotrans Ltd, regional networks of JSC Georgian State Electrosystem, JSC Telasi and JSC Energo-Pro Georgia.

See the link: Order No.86

Transmission Network Operating Limits
Information about Transmission Network Operating Limits for the Period from 1 October 2018 to 1 May 2019

The transmission network operating limits for the period from 1 October 2018 to 1 May 2019 were approved under Order No 644 of 3 October 2018 of JSC Georgian State Electrosystem. The basis for the Order is Article 47(3)(e) of the Network Code approved by Decree No 10 of 17 April 2014 of the Georgian National Energy and Water Supply Regulatory Commission and the Instructions for Establishing the Transmission Network Operating Limits approved by Order No 408 of 21 July 2016. The primary source of establishing the transmission network operating limits is information received from JSC United Energy System Sakrusenergo, Energotrans Ltd, regional networks of JSC Georgian State Electrosystem, JSC Telasi and JSC Energo-Pro Georgia.

See the link:Order No. 644

Transmission Network Operating Limits
Information about Transmission Network Operating Limits for the Period from 1 May 2018 to 1 October 2018

The transmission network operating limits for the period from 1 May 2018 to 1 October 2018 were approved under Order No 310 of 1 May 2017 of JSC Georgian State Electrosystem. The basis for the Order is Article 47(3)(e) of the Network Code approved by Decree No 10 of 17 April 2014 of the Georgian National Energy and Water Supply Regulatory Commission and the Instructions for Establishing the Transmission Network Operating Limits approved by Order No 408 of 21 July 2016. The primary source of establishing the transmission network operating limits is information received from JSC United Energy System Sakrusenergo, Energotrans Ltd, regional networks of JSC Georgian State Electrosystem, JSC Telasi and JSC Energo-Pro Georgia.

See the link:Order No. 310

Instructions for Submitting Operational Planning Data by the Electricity Producers to the Dispatch Licensee

The Instructions for Submitting Operational Planning Data by the Electricity Producers to the Dispatch Licensee were approved by Order No 86 of 9 February 2018 of JSC Georgian State Electrosystem. The basis for approval of the Instructions is Article 58(7) of the Network Code.

Instructions for Submitting Operational Planning Data by the Electricity Producers to the Dispatch Licensee

Emergency Action Plan

An Emergency Action Plan was approved under Order No 164 of 2 March 2018 of JSC Georgian State Electrosystem. The basis for approval of these instructions is Article 47(3)(i) of the Network Code.

See the link: Emergency Action Plan

Instructions for Testing Participation in Regulation of Voltage and Frequency of Power Generating Units/Aggregates

The Instructions for Testing Participation in Regulation of Voltage and Frequency of Power Generating Units/Aggregates According to the Preparedness Expressed by Power Generators were approved by Order No 122 of 21 February 2018 of JSC Georgian State Electrosystem. The basis for approval of the Instructions is Article 3 and Article 49(5) of the Network Code.

See the link: Instructions for Testing Participation

Instructions for Submitting Monthly, Quarterly and Annual Reports by Customers and Transmission Licensees to Dispatch Licensee

The Instructions for Submitting Monthly, Quarterly and Annual Reports by Customers and Transmission Licensees to Dispatch Licensee was approved by Order No 524 of 12 October 2017 of JSC Georgian State Electrosystem. The basis for approval of the Instructions is Article 44(5) of the Network Code.

See the link: Order No. 524

Transmission Network Operating Limits
Information about the Transmission Network operating limits for the period from 1 October 2017 to 1 May 2018

The Transmission Network operating limits for the period from 1 October 2017 to 1 May 2018 were approved by Order No 493 of 29 September 2017 of JSC Georgian State Electrosystem. The basis for the Order adoption is Article 47(3)(e) of the Network Rules approved by Resolution No 10 of 17 April 2014 of the Georgian Energy and Water Supply Regulatory Commission, and Instructions for Establishing Operating Limits approved by Order No 408 of 21 July 2016. The primary source of establishing the Transmission Network operating limits is the information received from JSC United Energy System Sakrusenergo, EnergoTrans LLC, regional networks of JSC Georgian State Electrosystem, JSC Telasi and JSC Energo-Pro Georgia.

See the link: Order No. 493

Change in the Transmission Network Operating Limits

The change applies to the Transmission Network operating limits for the period from 1 May 2017 to 1 October 2017.

Under Letter No 01/498 of 19 June 2017 of JSC United Energy System Sakrusenergo, change was made to Appendix No 9 to Order No 210 of 1 May 2017 of GSE on the Approval of the Transmission Network Operating Limits for the period from 1 May 2017 to 1 October 2017.

See the link: Order No. 329

Instruction for Ancillary / System Services

The basis of this document is Article 43(2) and (3.c) of the Network Code, which obliges a transmission system operator to determine which system services shall be provided when and by whom.

See the link - Downloadable file: Order No. 302

Transmission Network Operating Limits
Information about the Transmission Network operating limits for the period from 1 May 2017 to 1 October 2017

The Transmission Network operating limits for the period from 1 May 2017 to 1 October 2017 were approved by Order No 210 of 1 May 2017 of JSC Georgian State Electrosystem. The basis for adoption of the Order is Article 47(3)(e) of the Network Rules approved by Resolution No 10 of 17 April 2014 of the Georgian Energy and Water Supply Regulatory Commission, and Instructions for Establishing Operating Limits approved by Order No 408 of 21 July 2016. The primary source of establishing the Transmission Network operating limits is the information received from JSC United Energy System Sakrusenergo, EnergoTrans LLC, regional networks of JSC Georgian State Electrosystem, JSC Telasi and JSC Energo-Pro Georgia.

See link: Order No. 210

Instructions for Electricity (C.apacity) Demand Forecasts for the Stage of Long-Term and Operational Planning

The basis for the document is Article 40 of the Network Code, which obliges transmission system operators to make the electricity demand forecasts. The aim is to ensure to the extent possible consistent, effective and transparent process of making electricity (capacity) demand forecasts for the stage of long-term and operational planning.

See the link - Downloadable file: Instructions for Electricity (Capacity) Demand Forecasts for the Stage of Long-Term and Operational Planning_Geo

Transmission Grid Operating Limits

Information about transmission grid operating limits for the period from 1 October 2016 to 1 May 2017Transmission grid operating limits for the period from 1 October 2016 to 1 May 2017 were approved by Order No 639 of 28 September 2016 of JSC Georgian State Electrosystem. The basis for the abovementioned Order is Article 47(3)(e) of the Network Code approved by Resolution No 10 of 17 April 2014 of the Georgian National Energy and Water Supply Regulatory Commission (GNERC) and Instructions for Determining Transmission Grid Operating Limits approved by Order No 408 of 21 July 2016. Original source of determining the transmission grid operating limits is the information received from JSC United Energy System Sakrusenergo, Energotrans Ltd, Regional Networks of JSC Georgian State Electrosystem, JSC Telasi and JSC Energo-Pro Georgia.

See the link: Downloadable file: Order No. 639

Outage Planning Instructions

The basis for this document is Article 41 and Article 42 of the Network Code, which hold Transmission System Operators (TSOs) liable to plan the transmission grid and power plant outages. The document aims to ensure as consistent, effective and transparent as possible process of planning outages of any thermal/hydro power units or system elements.

Outage planning instructions – see the link - Downloadable file: Order No. 616

Instructions for conducting research to determine the transmission grid reliability

The basis for this document is Article 47(3)(f) of the Network Code, which holds the dispatch licensee liable to conduct relevant research to determine the reliability of the transmission grid. These Instructions aim to create the necessary theoretical base in the process of development of effective mechanism against emergency prevention through the conduction of appropriate research and the implementation of emergency simulation modeling.

See the link - Downloadable file: Order No. 560

Instructions for determination of the transmission grid operating limits

The basis for this document is Article 47(3)(e) of the Network Code, which holds the dispatch licensee liable to determine the transmission grid operating limits. Determination of the operating limits will further increase the reliability, stability and safety of the system.

See the link – Downloadable file: Order No. 408

Regime processing methods and procedures by using mathematical models for the transmission grid planning purposes

The basis for this document is Article 34 of the Network Code, which holds the dispatch licensee liable to determine appropriate methods and procedures.

See the link – Downloadable file: Order No. 387

Procedures for the collection of data from electricity meters/recording devices and their transfer

The basis for this document is Article 69(4) of the Network Code, which holds the dispatch licensee liable to determine the procedures for the collection of data from electricity meters and their transfer.

See the link – Downloadable file: Order No. 382

The list and form of standard data of transmission grid planning

The basis for this document is Article 32(6) and (10) of the Network Code, which holds the power system participants liable to submit data to the dispatch licensee under the procedure and in the manner as prescribed by the same provisions.

See the link – downloadable file: List and form of standard data for the network planning_Geo.

The list and form of detailed (additional) data of transmission grid planning

The basis for this document is Article 32(6) and (10) of the Network Code, which holds the power system participants liable to submit data to the dispatch licensee under the procedure and in the manner as prescribed by the same provisions.

See the link - Downloadable file: List and form of detailed (additional) data for the network planning_Geo.